PROJECT
ADDRESS
STATUS
Railroad Grade Separation, Jurupa Avenue - New
Jurupa Ave/UPRR
under construction
ADA Footpath Improvements FY 07-08
Various
under construction
Airport Noise and Drainage Control Project
6951 Flight Rd
completed
Airport Taxiway A
6951 Flight Rd
completed
Airport Terminal Building Patio Cover
6951 Flight Rd
completed
Airport Terminal Building Remodel
6951 Flight Rd
under construction
Antioch Ave Cul-de-Sac
Antioch Ave at Hillside Ave
under construction
Arlington Ave Sidewalk Extension (Tyler to Van Buren)
Arlington Ave - Tyler to Van Buren
completed
Arlington Fire Station Realignment
9449 Andrew St
completed
Arlington Heights Sports Park - New
Van Buren Blvd/Cleveland Ave
under construction
Arlington Library Expansion and Improvements
4015 Jackson St
completed
Banbury Dr Storm Drain
Banbury Dr
under construction
Citywide Curb, Gutter and Sidewalk Repair FY 2007/08
Various
under construction
Citywide Traffic Modification Project - New
various
under construction
Citywide Wheelchair Ramp Construction FY 06/07
various
completed
Citywide Wheelchair Ramp Construction FY 07/08
Various
completed
Curb, Gutter and Sidewalk Repair FY 06/07
Various
completed
Dewey Ave Sidewalk Installation and Paving Rehab (Brockton to Streeter)
Dewey Ave - Brockton to Streeter
completed
Dufferin Water Main Replacement
Dufferin Ave - Jefferson to Washington
completed
Electric Service Relocation for Jurupa Railroad Grade Separation
Jurupa Ave/UPRR
under construction
Emergency Vehicle Preemption System
Various
under construction
EOC and Fire Training Center - New
8095 Lincoln Ave
completed
Fiber Optic Line Extensions to 26 City Facilities
various
under construction
Hughes Alley Medians
Hughes Alley/Park Sierra Dr
completed
Irving Bridge Replacement at Gage Canal
Irving St
completed
Jones Ave and Hole Ave Sewer Main Relocation
Jones/Hole Avenues
completed
La Sierra Median Improvements
La Sierra Ave - Spaulding to Pierce
completed
La Sierra, Magnolia, and Iowa Avenues Traffic Signal Interconnect Systems - New
La Sierra/Magnolia/Iowa Avenues
under construction
Lincoln Police Station Improvements
8181 Lincoln Ave
completed
Magnolia Center Water Main Replacement
SR 91/Washington/Madison/Magnolia
under construction
Main Runway Replacement
6951 Flight Rd
completed
Mercury Vapor Lighting Replacement
various
under construction
Minor Street Rehab FY 07/08
Various
under construction
Mitchell/Norwood Intersection Improvements
Mitchell/Norwood
under construction
Monroe Street Channel Cover
Monroe Street
completed
Monticello Storm Channel Repairs
California/Colorado
under construction
Mountain View Park Playground
6241 Wiehe
out to bid
Myrtle Ave and Rockledge Drive Sewer
Rockledge Dr/Myrtle Ave
completed
Northside Taxiway Project - Phase I
6951 Flight Rd
in design
Norwood/College Water Main Replacement
Norwood/College Avenues
completed
Parking Lot Rehabilitation
Various
completed
Railroad Quiet Zones
BNSF Railroad
in design
Ramona Main Replacement
San Vicente Avenue/Monticello Avenue
completed
RERC Units 3 & 4 - New
5901 Payton Ave
out to bid
Right Turn Pocket Extension at Magnolia Ave/Van Buren Blvd
Magnolia Ave/van Buren Blvd
completed
Riverside Transmission Reliability Project (RTRP) - New
Various
in design
Safe Pathways to School
Various
out to bid
Septage Receiving Station Access Road
Acorn Street - Jurupa Ave to the WQCP
under construction
Sewer Main Relocation as a part of the Magnolia Ave Railroad Grade Separation
Magnolia Ave
under construction
Sewer Trunk Main Condition Assessment
Acorn/Magnolia/Van Buren
underway
Sidewalk Construction 2007/08
Various
under construction
Sidewalk Construction FY 06/07
Various
completed
Street Improvements FY 06/07
Various
completed
Street Rehabilitation FY 06/07
Various
under construction
Sub-Transmission Project (STP) - New
various
in design
Tequesquite Arroyo Sewer Trunk Line - Phase 2
Various
in design
Tyler/Riverside Freeway Interchange/Grade Separation - Phase I
Tyler/Riverside Freeway
in design
Underground Utilities (Van Buren Blvd from Andrew to Garfield) - Conversion
Van Buren Blvd - Andrew to Garfield
completed
Underground Utilities (Victoria Ave from Adams to St. Lawrence) - Conversion
Victoria Ave - Adams to St. Lawrence
under construction
Underground Utilities (Victoria Ave from Maude to Washington) - Conversion
Victoria Ave - Washington to Maude
in design
Underground Utilities (Victoria Ave from St. Lawrence to Jefferson) - Conversion
Victoria Ave - St. Lawrence to Jefferson
under construction
Van Buren Street Widening (Andrew to Garfield)
Van Buren Blvd - Andrew to Garfield
completed
Van Buren/Riverside Freeway Interchange - Replacement
Van Buren/Riverside Freeway
in design
Various Street Improvements
Various
under construction
Victoria Avenue Improvements
Victoria Ave
under construction
Victoria Booster Pumping Station Rehab
Victoria Ave/Myrtle Ave
under construction
Villegas Park Basketball Court and Stage Cover Improvements
7240 Marguerita Ave
completed
Water Line Relocation for Van Buren Blvd Bridge Replacement
Van Buren/Riverside Freeway
in design
Water Main Replacement as a part of the Jurupa Railroad Grade Separation
Jurupa Ave/UPRR
completed
Wayne Court Sidewalk Improvements project
Wayne Ct
completed
WCQP - Recycled Water Pump Station
5950 Acorn St
out to bid
Wheelchair Ramp Construction FY 07/08
Various
under construction