| Railroad Grade Separation, Columbia Avenue - New | Columbia Ave/BNSF | completed |
| Railroad Grade Separation, Iowa Ave - New | Iowa Ave/BNSF | in design |
| Railroad Grade Separation, Jurupa Avenue - New | Jurupa Ave/UPRR | completed |
| Railroad Grade Separation, Magnolia Avenue - New | Magnolia Ave/UPRR | under construction |
| Railroad Grade Separation, Third Street - New | Third St/BNSF | in design |
12th St Water Distribution Main Replacement - Phase II | 12 St | out to bid |
| 14th St Underpass Slope Paving | 14th St | under construction |
| ADA Footpath Improvements FY 07-08 | Various | completed |
| Battery Back Up Systems | Various | completed |
| Carlson Park Lighting and Parking Lot Improvements | 4700 Buena Vista Dr | completed |
| Center Street Extension | Center St - N Orange to Placentia Ln | completed |
| Citywide Curb, Gutter and Sidewalk Repair FY 06/07 | Various | completed |
| Citywide Curb, Gutter and Sidewalk Repair FY 2007/08 | Various | completed |
Citywide Curb, Gutter and Sidewalk Repair FY 2010-11 | Various | under construction |
| Citywide Traffic Modification Project - New | various | completed |
| Citywide Wheelchair Ramp Construction FY 06/07 | various | completed |
| Citywide Wheelchair Ramp Construction FY 07/08 | Various | completed |
| Citywide Wireless Traffic Signal Communications | Various | completed |
Convention Center Renovation and Expansion | 3343 Orange St | in design |
| Dales Senior Center | 3936 Chestnut St | in design |
| Dewey Ave Sidewalk Installation and Paving Rehab (Brockton to Streeter) | Dewey Ave - Brockton to Streeter | completed |
| Downtown Beautification Project | Main St - 10th to 5th | completed |
| Downtown Fire Station | Corner of University Ave and Lime St | in design |
| Downtown Mall Water Main Replacement | Downtown | completed |
| Downtown Raincross Pedestrian Lighting | Downtown | completed |
| Downtown Sewer Replacement | Various | completed |
Downtown Traffic Signal Modification Project | Various | under construction |
| E. La Cadena Sewer Capacity Improvements | E La Cadena/Columbia/Spring Garden/Palmyrita | completed |
| Electric Service Relocation for Columbia Railroad Grade Separation | Columbia Ave/BNSF | completed |
| Electric Service Relocation for Jurupa Railroad Grade Separation | Jurupa Ave/UPRR | completed |
| Electric Service Relocation for Magnolia Ave./UP Grade Separation | Magnolia Ave/UPRR | under construction |
| Emergency Vehicle Preemption System | Various | completed |
| Evergreen Cemetery - Curb, Gutter and Street Rehabilitation | Pine St | completed |
| Fairmount Park Improvements | 2601 Fairmount Blvd | in design |
| Fairmount Park Lake Rehabilitation - Phase I | 2601 Fairmount Blvd | completed |
| Fairmount Park Lake Rehabilitation - Phase II | 2601 Fairmount Blvd | in design |
| Fairmount Park Lighting and Paving Improvements | 2601 Fairmount Blvd | completed |
| Fairmount Park Playground | 2601 Fairmount Blvd | completed |
| Fiber Optic Line Extensions to 26 City Facilities | various | under construction |
| Fox Performing Arts Center - New | 3801 Mission Inn Ave | completed |
| Hunter 12kV Service Upgrade | 1731 Marlborough Ave | completed |
| Hunter Hobby Park Improvements | 1400 Iowa Ave | under construction |
| Hunter Park/ Northside Street Improvements | Various | under construction |
| Hunter Park/Northside Street Improvements | Various | completed |
| Hunter Substation Additions and Upgrades | 1731 Marlborough Ave | completed |
| La Sierra, Magnolia, and Iowa Avenues Traffic Signal Interconnect Systems - New | La Sierra/Magnolia/Iowa Avenues | completed |
| Magnolia Center Water Main Replacement | SR 91/Washington/Madison/Magnolia | completed |
| Magnolia Fire Station Improvements | 6395 Riverside Ave | completed |
| Main Library Expansion and Improvements | 3581 Mission Inn Ave | in design |
| Main St Renovation | Main St - Columbia to Placentia | under construction |
| Main St Water Main Extension | Main St - Columbia Ave to Placentia Ln | under construction |
| Market Street at 60 Freeway - Street and Landscape Improvements | Market St/SR 60 | completed |
| Massachusetts Ave Street Improvements | Massachusetts Ave | under construction |
| Mercury Vapor Lighting Replacement | various | completed |
| Metropolitan Museum Seismic Retrofit/Rehabilitation | 3580 Mission Inn Ave | in design |
| Minor Street Rehab 08-09 | Various | under construction |
| Minor Street Rehab FY 07/08 | Various | completed |
Misc Street Improvements at Various Locations | Various | under construction |
| Mission Inn Ave Improvements | Mission Inn Ave - Market St and Fairmount Blvd | completed |
| Mission Inn Avenue Improvements | Mission Inn Ave | completed |
| Mission Inn Avenue Sewer Main Replacement | Mission Inn Ave | completed |
| Mitchell/Norwood Intersection Improvements | Mitchell/Norwood | completed |
| Mt Rubidoux Park Improvements | 4706 Mt Rubidoux St | completed |
| Mulberry Well Discharge Pipeline | 9th St/Vine St | completed |
| Mulberry Well Rehab | 9th St/Vine St | completed |
| Municipal Auditorium Improvements | 3485 Mission Inn Ave | in design |
| Northside Fire Station - New | 1077 Orange St | completed |
| Parking Garage 1 Rehab | Orange/Mission Inn | completed |
| Parking Garage 2 Rehab | Orange/University | completed |
| Parking Garage 7 | Market Street - Adjacent to Fox Theatre | in design |
| Parking Lot Rehabilitation | Various | completed |
| Pellisier Ranch Water Transmission Line Extension | Center St/Stephens Ave | completed |
| Plaza 12kV Service Upgrade | 3716 Elizabeth St | completed |
| Plaza Transformer Addition | 3706 Elizabeth St | completed |
| Railroad Quiet Zones | BNSF Railroad | in design |
| RCC Joint Use Aquatics Facilities - New | 4800 Magnolia Ave | under construction |
| Rutland Park Renovation | 7000 Rutland Ave | completed |
| Safe Pathways to School | Various | completed |
| Security System Upgrade | Various | under construction |
| Sewer Trunk Main Condition Assessment | Acorn/Magnolia/Van Buren | completed |
| Shamel Park/Magnolia Little League Ballfield Rehabilitation | 3650 Arlington Ave | completed |
| Sidewalk Construction 2006/07 | Various | completed |
| Sidewalk Construction 2007/08 | Various | completed |
| Spruce Street and Russell Street Improvements | Spruce/Russell St | completed |
| Street and Alley Improvements | Martin Luther King Dr | completed |
| Street Improvements | Various | under construction |
| Street Improvements FY 06/07 | Various | completed |
| Street Rehabilitation 09/10 | Various | under construction |
| Street Rehabilitation FY 06/07 | Various | completed |
| Sub-Transmission Project (STP) - New | various | in design |
| Tequesquite Arroyo Sewer Trunk Line - Phase I | Tequesquite Arroyo | under construction |
| Tequesquite Arroyo Sewer Trunk Line - Phase II | Various | in design |
| Tequesquite Park - New | south of Mt Rubidoux | in design |
| Traffic Signal Modifications | Various | under construction |
| Traffic Signals and CCTV Camera Installation | Various | completed |
| University/Redwood Traffic Circle | University/Redwood | completed |
| Victoria Avenue Improvements | Victoria Ave | completed |
| Water Line Relocation for Columbia Ave Railroad Grade Separation | Columbia Ave/BNSF | completed |