Dewey Ave Sidewalk Installation and Paving Rehab (Brockton to Streeter)
Project Photograph 1
  Click photo for larger image
ADDRESS: Dewey Ave - Brockton to Streeter
Cost: $920,697
Status: completed
Start Date: 2006
End Date: 2007

Description

This project includes construction of curb and gutter, sidewalk, median landscaping, asphalt pavement widening and asphalt pavement rehabilitation along Dewey Avenue between Streeter Avenue and Brockton Avenue.

Additional Images

Project Photograph 2
Click photo for larger image